A shop crane makes engine pulls easy, which is why overloads and bad slings sneak up. This checklist inspects the crane, hook, chain and sling, and shows how the sling angle raises the load on each leg.

Why it matters

A hoist is rated by capacity, and the capacity drops as the boom is extended. Slings gain tension as the legs spread. Frequent checks catch wear before a failure drops a load. Follow the rating plate, the manufacturer and OSHA rules, and never stand under a suspended load.

Step by step

  1. Read the rating plate, then note capacity for each boom position and compare it with the weight of the load.
  2. Inspect the frame, welds, casters and boom pin for cracks, bends and missing hardware, and tag out any damaged crane.
  3. Check the hydraulic jack for leaks and test that it holds a light load without drifting.
  4. Inspect the hook for spread, twist and a working latch, and measure chain link diameter against the new size.
  5. Check slings for cuts, burns, broken strands, chemical damage and an unreadable tag, and discard any with doubts.
  6. Lift a few inches, pause, check balance, then raise and move slowly, keeping hands and body outside the load path.

Worked example

Illustrative: A 2-ton crane is rated 4,000 lb with the boom retracted. An engine weighs 2,600 lb on a two-leg sling at 60 degrees from horizontal. Tension per leg = 2,600 / (2 x 0.866) = 1,501 lb. At 30 degrees the same load is 2,600 / (2 x 0.5) = 2,600 lb per leg. A chain link new at 0.50 in measures 0.45 in, so 0.05 / 0.50 = 10 percent wear, to compare with the maker limit.

Printable worksheet: shop crane inspection

  • Crane, rating plate capacity and boom position: ____________________
  • Load weight ______ lb ; within capacity for that boom position (yes or no): ______
  • Sling angle from horizontal ______ ; sine ______ ; leg tension = load / (2 x sine): ______ lb
  • Chain link new ______ in ; measured ______ in ; wear percent = difference / new x 100: ______
  • Hook latch and throat opening: ____________
  • Sling tag legible ; cuts or burns found: ______
  • Inspected by ______ on (date) ______ ; tagged out (yes or no): ______

Common mistakes

  • Using the retracted-boom capacity when the boom is extended, which exceeds the real limit.
  • Using a shallow sling angle to fit a tight space, which multiplies the tension on each leg.
  • Keeping a sling with an unreadable tag because it looks fine.
  • Standing under or beside the load for a closer look.

Frequently asked questions

Who can inspect my shop crane?

You can do the frequent inspection, but an annual review by a qualified person is a common practice. Ask your insurer, OSHA or your state program what applies, and keep the dated log.

Can I extend the boom to reach farther?

Only within the capacity listed for that boom position. The rated load drops as it extends, so read the plate and the manual and move the crane closer if you can.

When do I throw out a sling?

When it shows cuts, burns, broken strands or chemical damage, or when the tag is gone. Follow the maker rejection criteria, and when in doubt replace it.